Union Pacific Glidden Sub Double Tracking Project – Update from Chimney Rock
Let’s continue with my coverage of Union Pacific’s project to add 5 miles of double track at the far east end of its Glidden subdivision. This post will cover the vicinity near MP 15, in the vicinity of the Chimney Rock Drive grade crossing, over the 6-week period between October 4 and November 21, 2012.
Looking east toward Heacker on October 4, 2012, the roadbed appears to be substantially completed and rail for the new main has been delivered.
West of Chimney Rock, fill material is still being delivered to build up the subgrade.
Just over 2 weeks after the above images were taken, delivery and placement of crossties was taking place east of Chimney Rock on October 19th.
It’s an interesting process how the crossties come off the truck and are placed on the roadbed.
Moving forward to November 21, 2012, the new double track grade crossing for Chimney Rock Drive has been installed. The next two images are looking eastward from the west side of the grade crossing.
Looking east down the new main, it’s almost straight rail.
The view westward from Chimney Rock :
The next post will cover the area around Hillcroft Avenue.